Use Summary Level Planning Packages (SLPP) to plan future work and track effort for long-term contract programs. SLPPs have an allocated budget, but do not have a detailed work or task plan. The budget for this far-term effort requires being at a level above the control account. But not at such a level that the budget is considered an undistributed budget.
You can track the SLPP effort by its association to a CWBS element. Define summary level planning packages for CWBS elements that will be delivered in the future. Future work is typically work that is scheduled no earlier than 12 months from the current reporting period.
You can convert SLPP into control accounts or into work packages on an existing control account associated to a CWBS element.
SLPPs are a type of summary planning package for those deliverable Budgets (BAC) that are in the far future. BAC is rolled up to the CWBS as part of the Performance Measurement Baseline (PMB). BAC is evenly distributed between the SLPP start and finish date.
|