Autoschedule Projects from a Finish Date

You can autoschedule projects from a finish date to help you find out on which date your project has to start in order to meet a required finish date. When you schedule your project based on its finish date, autoschedule performs three traversals of the project. In the second and third traversals, it goes over the tasks backward first and enforces finish constraints over start constraints so that the project is scheduled to start as late as possible.

When you run autoschedule using a project's finish date, it does the following:

Follow these steps:

  1. Open the Project ribbon.
  2. Click Autoschedule in the Schedule group.
  3. Select the Schedule from Finish Date check box to perform a backwards schedule from a defined deadline date.

    The Start Date field toggles to the Finish Date field. The current project finish date displays in the Finish Date field.

  4. Enter the project's anticipated finish date in the Finish Date field, and click OK.

More information:

Autoschedule Projects

Define the Scheduling Constraints for the Task