Rebaseline Projects

Use the Set Baseline dialog to rebaseline your project. When you rebaseline your project, the current baseline is replaced with the new baseline data.

Note: When you choose to rebaseline the view or selected tasks, the project baseline values are not updated.

You must select all levels of the WBS to rebaseline your project, view, or selected tasks. When you rebaseline tasks that have changed, such as changes to a resource's ETC, the data is not rolled up to the summary task level. Data, however, is rolled down to a phase's tasks when you rebaseline at the summary task level.

Follow these steps:

  1. Open the Project ribbon.
  2. Click Define in the Baselines group.
  3. Select the following options:
  4. Click OK.
  5. Click Yes to confirm that you want to overwrite the prior version of the baseline data with the new version, when prompted.

More information:

Baseline Projects

Set Baselines