Pending Estimates Portlet

Depending on whether less or more time is required for a task, a team member can increase or reduce the ETC on a task. They can do this using Timesheets. However, the project manager approves the modifications before the change is reflected in CA Clarity PPM. The Pending Estimates portlet lets you view all the variables associated with a task. Based on the variables, you can accept or deny any modified ETCs.

This portlet displays the following details:

Stoplight

Displays a stoplight indicating how the ETC was modified.

Stoplights:

Project

Displays the name of the associated project. Click the project name link to open the project properties page and edit the project.

Task

Displays the name of the associated task. Click the task name link to open the task properties page and edit the task.

Resource

Displays the name of the associated resource. Click the resource link to open the assignment properties page for the resource.

Start

Displays the date of starting the associated task.

Finish

Displays the date of completing the associated task.

Pending ETC

Displays the amount of ETC added to the timesheet.

Plan ETC

Displays the amount of ETC initially assigned to the task.

Pending Actuals

Displays the amount of unposted actuals for the task.

Adjusted Plan ETC

Displays the adjusted planned ETC amount (Planned ETC - Pending Actuals).

Recommended Change in ETC

Displays the amount of ETC used based on the modified ETC entered in the timesheet.