Track Resources by Total Actual Usage

You can record periodic actual usage using the Resources tab on the Task Properties dialog or by editing a view that displays the Actual field name.

Follow these steps:

  1. Open a view that displays the task detail pane.
  2. Select a task and click in the cell displaying total actual usage.
  3. Enter the total actual usage for each applicable cell on the timescale.