Multiple Projects and Subnets › Master Project and Subprojects › Set Resource Allocation to Subprojects
Set Resource Allocation to Subprojects
To set a resource's allocation to a subproject, edit it at the subproject level. This field is inactive in the master project. You can set the allocation on a subproject in the following ways:
- If you are using Open Workbench with CA Clarity PPM, you can set the allocation in CA Clarity PPM by creating allocation segments.
- You can also set a resource's allocation manually by editing the availability in the timescale section of the view. To do this, add the Availability field to a spreadsheet view, such as the Gantt Chart view.