For Percent Complete to display correctly when rolled up to the activity or phase levels, first set a baseline. Select the Pct Complete option from the % Displayed drop-down list in the Gantt dialog. Also assign the billing rates to the resources in the Resource Properties dialog. All dates that are displayed in the Gantt chart are equally distributed along its width.
The following procedure explains how to see baseline data and how to modify the Gantt chart.
Follow these steps:
Displays a bar that indicates the percent of the work.
Values:
Specifies whether to display the baseline bars beside the task progress bars. When selected, the Stacked check box is enabled.
Specifies whether to display bars indicating the amount of float in tasks. Float is the number of days that initiation or completion of a task can be delayed without adversely affecting the project finish date. Float is calculated using the following formula: Late Start - Early Start.
Specifies whether to superimpose baseline data on the existing project data.
Specifies whether to display dependencies. When selected, you can view and edit dependency relationships directly in a Gantt chart.
Specifies whether to prevent users from manually extending or shortening the Gantt bars on the Gantt chart.
Specifies whether to show summary task progress.
Select to display bars indicating breaks in task-related work, such as holidays and weekends.
Defines the maximum number of days to filter segments.
Defines the width of the Gantt chart in pixels.
Specifies whether to use the current system date as the Gantt chart's display date.
Specifies whether to use the start date of the first task in the project as the Gantt chart's display date.
Specifies whether to use the As-of date as the Gantt chart's display date.
Note: Enter this date on the Advanced tab on the Project Properties dialog.
Specifies whether to use the finish date of the last task in the project as the Gantt chart's display date.
Specifies whether to use nonwork days as the Gantt chart's display date.
Specifies whether to use the end of the current time period as the Gantt chart's display date.
|