The task priority controls the order in which tasks are scheduled during autoschedule, subject to dependencies and task and resources constraints. Autoschedule, therefore, schedules tasks with higher priority ahead of tasks with lower priority. Use the General tab on the Task Properties dialog to define a task's priority or priority inheritance. If you do not specify priority for a task, autoschedule uses the priority of its parent task, or the next highest WBS level. If no priority is defined, autoschedule uses the default value (10).
Autoschedule schedules task priority as follows:
For dependencies, autoschedule assumes that a predecessor task has a priority at least equal to its successor. In some cases, dependency relationships override individual task priority during the scheduling process.
|