Labor Class

You can use the following attributes when querying labor:

Labor Baseline FTEs

Displays the current baseline value of total work for labor resources as measured in full-time equivalent (FTE).

Labor Actuals FTEs

Displays the total number of posted actuals for labor resources as measured in full-time equivalent (FTE).

Labor ETC FTEs

Displays the total of estimated to complete (ETC) work for labor resources as measured in full-time equivalent (FTE).

Labor Allocation FTEs

Displays the total planned allocation for labor resources as measured in full-time equivalent (FTE).

Labor Hard Allocation FTEs

Displays the total hard allocation for labor resources as measured in full-time equivalent (FTE).

Labor Available FTEs

Displays the total availability for labor resources as measured in full-time equivalent (FTE).

Labor Baseline FTE %

Displays the current baseline value of total work for labor resources as measured in percent availability of a full-time equivalent (FTE).

Labor Actual FTE %

Displays the total number of posted actuals for labor resources as measured in percent availability of a full-time equivalent (FTE).

Labor ETC FTE %

Displays the total of estimated to complete (ETC) work for labor resources as measured in % Availability of a full-time equivalent (FTE).

Labor Allocation FTE %

Displays the total planned allocation for labor resources as measured in percent availability of a full-time equivalent (FTE).

Labor Hard Allocation FTE %

Displays the total hard allocation for labor resources as measured in percent availability of a full-time equivalent (FTE).

Labor Available FTE %

Displays the total availability for labor resources as measured in percent availability of a full-time equivalent (FTE).

Labor Baseline Hours

Displays the current baseline value of total work for labor resources as measured in hours.

Labor Actual Hours

Displays the total number of posted actuals for labor resources as measured in hours.

Labor ETC Hours

Displays the total of estimated to complete (ETC) work for labor resources as measured in Hours.

Labor Allocation Hours

Displays the total planned allocation for labor resources as measured in hours.

Labor Hard Allocation Hours

Displays the total hard allocation for labor resources as measured in hours.

Labor Available Hours

Displays the total availability for labor resources as measured in hours.

Labor Baseline Cost

Displays the current baseline cost (BAC) of total work for labor resources.

Labor Actual Cost

Displays the cost of posted actuals for labor resources.

Labor ETC Cost

Displays the total cost of estimated to complete (ETC) work for labor resources.

Labor Allocation Cost

Displays the total cost of planned allocation for labor resources.

Labor Hard Allocation Cost

Displays the total cost of hard allocation for labor resources.