Define Resource Actual Usage on Tasks
If you previously recorded a resource's periodic actual usage, you cannot change the total actual usage directly in a view. The following procedure explains how to record a resource's total actual usage.
Follow these steps:
- Open a view that displays the task detail pane.
- Right-click a task and click Assignments from the shortcut menu.
- Select the name of the resource for which you want to record total actual usage in the Assigned Resources grid.
- Complete the following fields to update the resource detail section of the view to reflect the resource's actual usage on the task:
- Actual
-
Defines the cumulative actual usage.
- Act Thru
-
Defines the last date through which actuals have been captured on the task for the resource.
- Click OK.
More information:
Define the Resources Properties
Resource Loading Patterns
Add Resources to Tasks
Track Resources by Total Actual Usage