How to Staff a Service Team › Edit Planned and Committed Allocations for a Service
Edit Planned and Committed Allocations for a Service
As a service manager, you want to answer the following questions:
- How much resource availability do I have for a service?
- Which resources are overbooked or under booked, and by how much?
You can examine the planned and committed allocation for a service by resource and by time period in a graph.
Follow these steps:
- Open a service.
- Click the Team menu and select Detail.
Allocations appear by resource, allocation, and time period.
- Scroll over a time period.
A note with a brief summary appears.
- Examine the time period columns and allocation colors. The columns are set to weekly by default, and always start with the current week.
- Yellow indicates resources that are allocated at or under availability for that time period.
- Red indicates resources that are over-allocated. The amount of time booked exceeds availability for that time period.
- Green indicates resource allocations to other investments, ideas, or services.
- To edit the time-related values, click in the graph. For example, you can edit the time cells for each resource.
- Save your changes.