Edit External Task Dependencies

You can edit dependency relationships for external dependencies using the Dependencies tab on the Task Properties dialog or using the External Dependencies dialog. You cannot move the dates on external tasks or modify it within your project; the externally linked task's properties are read-only and do not include resource or dependency information.

Note: You can only access the Dependencies tab on the Task Properties dialog if the externally dependent task has a predecessor relationship with the task in your project.

Follow these steps:

  1. Open the Projects ribbon.
  2. Click Dependencies in the External group.
  3. Locate the external dependency task you want to modify, and complete the following fields:
    Pred/Succ

    Specifies the task's dependency relationship.

    Default: Successor

    Options: Successor or Predecessor

    Type

    Specifies the constraint type to be placed on the task's start or finish date.

    Default: Finish-Start

    Options: Start-Start, Start-Finish, Finish-Start, or Finish-Finish

    Lag

    Defines the number that represents the days or percent to indicate the amount or time between, or overlapping, the task start or finish dates.

    Note: The constraint type used is the type you specify.

    Lag Type

    Specifies the lag type.

    Default: Daily

    Options: Daily or Percent

  4. Click OK.