Previous Topic: Create ResourcesNext Topic: Resource Role Assignments


Add Resources and Roles to Projects

You can add staff to your project by manually inserting a resource line item and entering the resource details directly in the resource detail pane of a view, such as the Gantt Chart view. To add a resource, right-click anywhere in the resource section, and click Insert in the shortcut menu. You can also copy resources from another project you have open in Open Workbench and paste them into your project.

If you are using Open Workbench with CA Clarity PPM, you can add resources or roles to your project from:

Note: You can also add a resource to a project by creating a resource in Open Workbench and then adding the resource to CA Clarity PPM.

Follow these steps:

  1. Click Project Properties in the application menu.
  2. Open the Resources tab.
  3. Select one of the following options to view the Global Resources list by role or by category:

    Note: If you are using Open Workbench with CA Clarity PPM and you have not defined resource categories in CA Clarity PPM, roles is selected and the list box is unavailable.

  4. Complete one of the following steps in the Global Resources grid:
  5. Click Add and click OK.

More information:

Create Resources

View the List of Resources Staffed on Projects

Remove Resources or Roles from Projects