Define the Resource's Calendar

Use the Calendar tab on the Resource Properties dialog to assign vacations, holidays, or other periods of unavailability. If you are using Open Workbench with CA Clarity PPM, use this calendar only to perform what-if scenarios.

Note: Set all days as either work days or holidays.

Follow these steps:

  1. Open a view that displays the resource detail pane.
  2. Right-click the resource and click Modify in the shortcut menu.
  3. Open the Calendar tab.
  4. Select a calendar from the Based on drop-down list.

    The resource calendar inherits the working days, holidays, and shift settings of this calendar.

    Options: USA, United States, or United Kingdom

    Default: USA

  5. Complete one of the following steps:
  6. Complete one of the following steps:
  7. Click OK.