Fulfill Resource Requisitions

Requests for named resources include a proposed resource making it easier for you to respond. To address requests for named resources, open a requisition and address it individually. Or, select multiple requisitions and propose them back to the project manager.

This page displays a histogram presenting more information about the resource. You see exactly how much the project manager requests on a weekly basis. The yellow part of the histogram represents the amount the resource is needed on this particular project. The green part represents amounts needed on other projects. The red shows where the resource is over-allocated.

Follow these steps:

  1. Open Home, and from Resource Management, click Resource Requisitions.
  2. Click the Person with List icon next to a requisition to access that requisition.
  3. Click Propose to propose the resource back to the project manager for the requested time and allocation amount.

    The Resource Requisitions page appears and refreshes the status of the requisition to "Proposed".

  4. To address multiple named requests:
    1. Select the list of named resources and click Propose to propose the allocations to the project manager.
    2. Edit the allocation amounts for the requested named resources directly in the grid.
    3. Select the list of named resources and click Propose to propose the allocations to the project manager.

    The Resource Requisitions page appears and refreshes the status of the requisition to Proposed.

  5. Confirm the changes in the resource histogram that displays how much the project manager requests on a weekly basis:
  6. If the Requisition Approval Required option for the project is turned off (no project manager approval required):