Insert a Task to a Specific WBS Location
When necessary, insert a task to a specific location in the work breakdown structure (WBS) in the Gantt view.
Follow these steps:
- Open the project.
- Open the Tasks menu and click Gantt.
- Select the check box against the project name, or click anywhere on the task row to insert the new task row below it. Then, perform one of these actions:
- Use the keyboard shortcut key:
- Windows: Press Insert.
- Macintosh: Press Ctrl+I.
- Click the Create New Task icon on the Gantt view.
- Complete the fields in the Create Tasks page. The following fields require explanation:
- % Complete
-
Defines the percent of work that has been completed when the task is partially completed.
Values:
- Zero. The task is not started.
- 1 through 99. The task has ETC or actuals posted and the task is not started.
- 100. The task is complete.
Default: 0
- Perform one of the following actions:
- Click the Save icon on the Gantt view toolbar.
- To enter a new task below and as a peer to this task, press Enter.
- Press Tab to move to the next field.