You define scheduling properties for the following reasons:
Follow these steps:
Defines the date to include data in time and budget estimates. This date is used in Earned Value Analysis (EVA) calculations, such as Budgeted Cost of Work Scheduled (BCWS) and drives the calculations for costs. ETC for a project is not scheduled on or before the As of Date.
Defines the percent of work that has been completed on the project, based on the percentage of completion of the tasks and subprojects. This field is displayed only if the % Complete Calculation Method is set to Duration or Effort.
Default: 0
Values: 0 through 100
Specifies the method to calculate the % Complete value for the project and tasks.
Values:
Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
Default: Manual
Note: Set the % Complete Calculation Method at the beginning of your project and do not change this value.
Important! Verify that the start and finish dates of tasks and assignments are the same or within the start and finish dates of the project. Else, the start and end dates of the project are automatically redefined as per the start and end dates of the tasks and assignments.
Indicates the tracking method that is used by resource assignments to enter time spent on project tasks.
Values:
Default: Clarity
Defines the charge code against which transactions for the project are charged. If you also define task-level charge codes on timesheets, then the task charge codes override this code.
Defines the set default OBS unit that is used when you add team staff members to this project. This OBS unit describes a staffing requirement, and can be a resource pool, a specific location, or a department. By mapping roles with OBS units and resource managers, the roles can be filled more accurately. The default staff OBS unit is used during capacity planning for analyzing demand against your capacity using the staff OBS as filter criteria.
Example:
Use the OBS to find out if you have enough capacity for programmers in Atlanta to fulfill the demand for programmers in that location.
Copyright © 2013 CA.
All rights reserved.
|
|