Close the Risk

Once the risk is successfully mitigated, change the status of the risk to Closed and enter the final resolution. A detailed resolution can help you recall the outcome of a risk response strategy when planning, or approaching future project risk plans.

Follow these steps:

  1. Open the project and click Risks/Issues/Changes.
  2. Open the risk.
  3. Change the Status to Closed.
  4. Enter how the risk was mitigated in the Resolution section.
  5. Save your changes.