Define Program Budget Properties

Though it is not required that you create a budget for a program, you can create a simple one. The budget applies only to the program, not to its subprojects. The financials page is not available for programs. However, you can use the planning page to create a detailed budget or forecast for the program.

You can view program budget data, and budget data generated from its subprojects, on the program Dashboard page.

Follow these steps:

  1. Open the program.

    The properties page appears.

  2. Open the Properties menu and click Budget.

    The budget page appears.

  3. Complete the following fields:
    Currency

    Select the currency to calculate the program budget and forecast values.

    Planned Cost

    Enter a planned cost for the entire program. The value you enter is distributed between the planned cost start and planned cost finish dates.

    Planned Cost Start

    Defines the start date for the budget. You have an option to use the program start date.

    Planned Cost Finish

    Defines the finish date for the budget. You have an option to use the program finish date.

    Planned Benefit

    Enter the anticipated financial benefit for this program. The value is distributed between the planned benefit start and finish dates.

    Planned Benefit Start

    Select the scheduled benefit start date.

    Planned Benefit Finish

    Select the scheduled benefit end date.

    Planned NPV

    The value in the field is calculated based on the following formula:

    Planned NPV = Planned Benefit - Planned Cost
    

    If you clear the Calculate Financial Metrics field, you can make the field available for data entry.

    Planned ROI

    The value in the field is calculated based on the following formula:

    Planned ROI = Planned NPV / Planned Cost
    

    Note: If you clear the Calculate Financial Metrics field, you can make the field available for data entry.

    Planned Breakeven

    The date and amount in this read-only field indicate the period and value at which the program becomes profitable.

    Note: If you clear the Calculate Financial Metrics field, you can make the field available for data entry.

    Calculate Financial Metrics

    Specifies if the Financial metric fields (Planned NPV, Planned ROI, and Planned Breakeven) are loaded automatically using the formulas listed in the field descriptions. Clear this field to make the financial metric fields available for data entry.

    Default: Selected

  4. Save the changes.

More information:

Monitor Program Performance