You can open the legend from the Gantt View toolbar. The Gantt chart displays the following indicators to specify the type or status of a task:
Indicator |
Description |
---|---|
Task. A task is an activity that is required to be accomplished within a time frame. Tasks define the project work, the staff member, and the resource that performs the work. |
|
Progress Through Bar |
|
Completed Task. A completed task is a task where its status is set to "Completed". |
|
Late Task. A late task is a task or milestone where the Finish date field value is later than the Baseline Finish date field value. |
|
Summary Task. A summary task is a task that has one or more subtasks nested beneath it. |
|
External Task displayed in the Gantt chart. An external task is a task in another project on which a task within the project has a dependency. |
|
Subproject displayed in the Gantt chart. A subproject is a project located within a master project. |
|
External Task displayed in the WBS. An external task is a task in another project on which a task within the project has a dependency. |
|
Subproject displayed in the WBS. A subproject is a project located within a master project. |
|
Milestone. Milestones are tasks that have a due date but not a duration (a period between a start and finish date). |
|
Completed task. A completed task is a task where its status is set to "Completed". |
|
Late task. A late task is a task or milestone where the Finish date field value is later than the Baseline Finish date field value. |
|
External Milestone. An external milestone task is a milestone in another project on which a task within the project has a dependency. |
|
Critical Path. The critical path determines the earliest finish date of the project. |
|
Link to hidden task. |
Note: The External Task and Subproject icons appear on the task-side of the WBS list, to the right of the task name. The other icons appear on the Gantt side of the view as part of task images.