Autoschedule and Publish

Use this procedure to publish the tentative schedule using the default options. When you autoschedule and publish, the new schedule replaces the plan of record (POR) and the project is unlocked.

Follow these steps:

  1. Open the project and click Tasks.

    The list page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Click the down arrow for the Autoschedule With Options icon in the Gantt view, and click Autoschedule with Publish.