How to Update Cost Totals
Update costs when you create or update a baseline, and when you change the task information - an input for earned value calculations. When earned value is used, update the total costs to view costs tied to ACWP, EAC (Cost), and ETC (T).
Use the following process to update the costs totals for your project:
- Schedule the Rate Matrix Extraction job to run periodically.
- Do one of the following:
- Update cost totals. The Update Earned Value Totals job runs.
- Schedule the Update Earned Value Totals job to run at recurring intervals based on how often you post actuals.
More information:
Create Baselines
Edit Baselines (Investments)
Task Cost Metrics