Previous Topic: View a List of Risks Associated with TasksNext Topic: Associate Existing Tasks with Risks


Create Key Tasks Associated to Risks

Follow these steps:

  1. Open the project and click Risks/Issues/Changes.
  2. Click the risk name.
  3. Click Associated Tasks.
  4. Click New.
  5. Complete the fields in the General section. The following fields require explanation:
    Milestone

    Specifies to designate the task as a milestone task. Milestones are tasks that have a due date but not a duration (a period between a start and finish date). Once saved, the Start field on the task properties page is locked.

    Default: Cleared

    Note: You cannot assign staff to milestones or designate them as summary tasks.

    Key Task

    Specifies whether you want to identify this task as a key task. A key task is significant in some way. For example, the start date of other tasks can depend on the key task.

    Example: If this task is one whose completion is essential to the start date of other tasks, then mark this task as a key task.

    Default: Selected

    Status

    Displays the status of the task based on the value of % Complete. This field is automatically calculated and updated based on the task % Complete value.

    Values:

    • Completed. Indicates that the ETC task is zero and the percentage completed is 100.
    • Not Started. Indicates that actuals are not posted and the percentage completed is zero..
    • Started. Displays when a resource posts actuals to the task assignment. The percentage completed on the task is more than zero and less than 100.

    Default: Not Started

    % Complete

    Defines the percent of work that has been completed when the task is partially completed.

    Values:

    • Zero. The task is not started.
    • 1 through 99. The task has ETC or actuals posted and the task is not started.
    • 100. The task is complete.
    • Default: 0
    Charge Code

    Defines the charge code for the task. Task-level charge codes supersede project-level charge codes where both are specified.

    Must Start On

    Defines the date on which the task is required to start. This date is used as a date constraint during autoscheduling.

    Must Finish On

    Defines the date on which the task is required to finish. This date is used as a constraint during autoscheduling.

    Start No Earlier Than

    Defines the earliest possible start date for a task. This date is used as a constraint during autoscheduling.

    Start No Later Than

    Defines the latest possible start date for the task. This date is used as a constraint during autoscheduling.

    Finish No Earlier Than

    Defines the earliest possible finish date for a task. This date is used as a constraint during autoscheduling.

    Finish No Later Than

    Defines the latest possible finish date for a task. This date is used as a constraint during autoscheduling.

    Exclude from Autoscheduling

    Specifies excluding the dates for this task during the auto-scheduling process.

    Default: Cleared

    Required: No

    Note: This field works with the Schedule Assignments on Excluded Tasks field on the auto-schedule page. Suppose, you exclude the task from auto-scheduling. But you specify allowing changes to excluded task resource assignment dates during auto-scheduling. The auto-schedule process changes the task resource assignment dates, while remaining within the start and finish dates for the task.

  6. Save and submit the changes.