Risks, Issues, Change Requests, and Action Items › Risks › How to Create Risks › Create Risks from Issues
Create Risks from Issues
You can create risks from existing issues. Basic information from common fields is carried over to the new issue for easy setup. You can link back to the originating issue from the risk for easy navigation between the records. In addition, you can manually associate risks or issues to each other. Manual association is useful for understanding the relationships between the risks and issues, providing better overall management of a project.
Follow these steps:
- Open the project and click Risks/Issues/Changes.
- Open the Risks/Issues/Changes menu and click Issues.
- Click the name of the issue.
- Click Create Risk.
- Complete the fields in the General section. The following fields require explanation:
- Category
-
Defines the category to which the risk belongs.
Values:
- Flexibility - The project is not adaptable.
- Funding - The project funding is not allocated or is available with constraints.
- Human Interface - The user interface (UI) is poorly defined.
- Implementation - Uncertainties exist in the implementation effort and user acceptance
- Interdependencies - The project is dependent on other projects.
- Objectives - The requirements, objectives, scope, and benefits are unreasonable, unclear, not measurable, and not verifiable.
- Organizational Culture - The project requires changes to the organization culture, business processes, procedures, or policies.
- Resource Availability - The internal resource availability is uncertain and external resources are required.
- Sponsorship - The sponsorship is not clearly identified and committed.
- Supportability - It is not easy to support the project in the future and requires major updating.
- Technical - The project technology is unproven and new internal or external expertise is required.
- Owner
-
Defines the name of the resource who is managing the risk. This resource is responsible for verifying that the risk is managed and tracked appropriately through its lifecycle.
Default: The resource that is currently logged in.
- Creator
-
Displays the name of the resource who created this risk.
Default: The resource currently logged in.
- Complete the fields in the Details section. The following fields require explanation:
- Risk Symptoms
-
Defines the symptoms that identify this item as a risk.
- Impact Description
-
Displays a description of the result the risk had on the project.
- Risk Impact Date
-
Displays the date when the repercussions from the risk impacted the project.
- Target Resolution Date
-
Displays the target date of resolving the risk.
- Assumptions
-
Displays the assumptions that determined the risk.
- Associated Risks
-
Defines the risks within this project that are associated with this risk. You can only link this risk to risks within this project.
- Associated Issues
-
Defines the issues within this project that are associated with this risk. You can only link this risk to risks within this project.
- Response Type
-
Defines the type of response you want to make with this risk.
Values:
- Watch. Use this type when you do not want to respond to a risk. This type is typically assigned for any risk whose calculated risk score is low. In other words, though risk probability or impact is not sufficient to warrant action, you still want to keep the risk open and monitor it.
- Accept. Use this type when the risk exposure is accepted, and in some cases, there is no intent to pursue the risk.
- Transfer. Use this type when you want to transfer the risk to a different project. Once transferred, you can close the risk.
- Mitigate. Use type when you want to apply a risk response strategy to resolve the risk.
Default: Watch
- Complete the fields in the Quantify Risk section. The following fields require explanation:
- Probability
-
Defines the probability that the impact can occur. The risk probability is used to calculate the risk exposure.
Values: Low (1), Medium (2), or High (3)
Default: Low
- Calculated Risk
-
Displays the score calculated based on the selections you make in the Probability and Impact fields.
Risk values:
- 4 - 6 (Yellow). The calculated risk is medium.
- 7 - 9 (Red). The calculated risk is high.
- 1 - 3 (Green). The calculated risk is low.
- Impact
-
Defines the effect of the particular risk on the project, determined by the risk effect on project performance, supportability, cost, and schedule. This value is used to calculate the risk exposure.
Values: Low (1), Medium (2), or High (3)
Default: Low
- Attach the documents, if any in the Attachments section.
- Complete the fields in the Resolution section. The following fields require explanation:
- Resolution
-
Defines the final resolution once the risk is mitigated. The resolution data is useful for recalling the outcome of a risk response strategy when planning or approaching future project risk plans.
- Residual Risks
-
Specifies the risks encountered or created within the project as a result of the mitigation taken to resolve the risk. Unlike associated risks, residual risks do not share similar outcomes, but result from an action you take in resolving a risk.
- Save the changes.
Copyright © 2013 CA.
All rights reserved.
|
|