The following table maps fields from Microsoft Project to fields on the scheduling properties page in CA Clarity PPM:
Microsoft Project |
CA Clarity PPM |
Notes |
---|---|---|
Start Date |
Start Date PRJ_PROJECTS: PRSTART |
|
Finish Date |
Finish Date PRJ_PROJECTS: PRFINISH |
|
Schedule From |
Start Imposed This field is not displayed by default. PRJ_PROJECTS: PRSTARTIMPOSED
Finish Imposed This field is not displayed by default. PRJ_PROJECTS: PRFINISHIMPOSED |
If this field is displayed, the Schedule From field is set to the Start Date when you open the project in Microsoft Project. Otherwise, Schedule From is set to the Finish Date. |
Status Date |
As Of Date PRJ_PROJECTS: PRASOF |
You cannot programmatically set this field to NA in Microsoft Project. If the As of Date in CA Clarity PPM is blank, the existing value in this field is retained. |
Priority |
Priority PRJ_PROJECTS: PRPRIORITY |
Priorities are translated between the range (0-1000) in Microsoft Project and the range (36-0) in CA Clarity PPM. |