Schedule Subnets

Use the following procedure to set up your project to calculate separate critical paths. Subnets are a set of project tasks that have dependencies among themselves, or a single task with no dependencies. During autoschedule, you can calculate and display separate critical paths for each subnet and for each task that does not have dependencies. Otherwise, only one critical path, the longest path, is calculated for the project.

Scheduling subnets has several key benefits:

Follow these steps:

  1. Open the project and click Tasks.

    The list page appears.

  2. Open the Tasks menu and click Gantt.

    The Gantt view appears.

  3. Click the down arrow for the Autoschedule With Options icon in the Gantt view.

    The autoschedule page appears.

  4. Complete the following field:
    Subnets

    Specifies to autoschedule to calculate the critical path for the entire project. When the field is selected, a separate critical path is calculated for each subnet.

    Default: Cleared

    Select the check box.

  5. Click Autoschedule.