You can apply estimates (ETC) across all tasks by editing and applying the ETC at the project level. Applying ETC at the project level distributes the ETC value across all the project tasks according to task duration, resource availability, and resource allocation. The current ETC assumes the new value.
Follow these steps:
The estimating properties page appears.
Defines the new estimate to apply across all the tasks in the project.
The new ETC is applied.