Previous Topic: Populate Cost Plans AutomaticallyNext Topic: Edit Cost Plans


How to Display Capital and Operating Costs

You can show operating and capital costs separately on the financial summary page and in a detailed financial plan. You can enter the cost information in the following ways:

Financial Summary Page

The financial summary page for an investment displays high-level operating and capitalization costs for planned and budgeted costs. You can edit the amounts on the financial summary until you create a cost plan of record (POR). When you create a POR, the fields for operating and capitalization costs in the planned and budgeted cost sections of the financial summary become read-only. The POR information updates the planned cost fields on the financial summary page automatically. The latest approved budget updates the budget fields.

Detailed Financial Plan

You can create a detailed financial plan manually, or you can populate the plan automatically from tasks or team allocations. To populate from task or team allocations, Cost Type must be selected as a grouping attribute. To populate cost and budget plans automatically with capital and operating costs, use one of the following methods:

Important! The procedures in this scenario describe the product navigation with no add-ins installed. If you have an add-in such as the PMO Accelerator installed, the navigation can vary.

The following diagram describes how a financial administrator displays capital and operating costs on summary and detailed financial plans.

Screen shows the flow for setting up to show capital and operating costs.

To display capital and operating costs, perform these steps:

  1. Review the prerequisites.
  2. (Optional) Manually update the budget page to display capital and operating costs.
  3. Select the method for collecting cost information and create the plan.
  4. Set the cost type for specific investment tasks.
  5. Set the capitalization percentage for investment team allocations.
  6. Verify that the capital and operating costs display correctly.

Back to Top

Review the Prerequisites

Complete the following setup tasks before beginning the procedures described in this scenario:

Back to Top

(Optional) Manually Update the Financial Summary Page to Display Capital and Operating Costs

To assist with high-level planning, you can manually add capital and operating amounts on the financial summary page. For example, you have a new project and must deliver high-level, planned cost estimates. You can enter estimates for operating and capital costs. Once you have created a cost plan of record (POR) or have an approved budget, these fields become read-only.

Follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type (for example, Projects).
  2. Open the investment and click Properties to open the menu.
  3. Click Budget.
  4. In the Planned Cost section, enter values for the following fields:

    Note: If the POR does not use the Cost Type grouping attribute, the Planned Operating Cost field summarizes all costs as operating.

    Planned Capital Cost

    Specifies the amount of capital cost that is planned for the investment. If the plan has a cost POR, the values from the POR populate this field and it becomes read-only.

    Planned Capital %

    Specifies the percentage of total cost that comes from capital. This read-only field is automatically calculated based on the Planned Cost field value.

    Planned Operating Cost

    Specifies the amount of operating cost that is planned for the investment. If the plan has a cost POR, the values from the POR populate this field and it becomes read-only.

    Planned Operating %

    The percentage of total costs that comes from operating. This read-only field is automatically calculated based on the Planned Cost field value.

  5. In the Budgeted Cost section, enter values for the following fields.

    Note: If Cost Type is not a grouping attribute, then all values are combined in the Budgeted Operating Cost field.

    Budgeted Capital Cost

    Specifies the amount of capital cost that is budgeted for the investment. This field is unavailable when:

    • A POR or approved budget exists. The value is populated from the approved budget. The field becomes read-only when a POR is created; however, if an approved budget does not exist, the budget fields are automatically populated with null cost values.
    • The Budget Equals Planned Values check box is selected and detailed financial plans do not exist.
    Budgeted Capital %

    Specifies the percentage of total budget costs that come from capital. This read-only field is calculated from the Budgeted Capital Cost field value.

    Budgeted Operating Cost

    Specifies the amount of operating cost that is budgeted for the investment. This field is unavailable when:

    • A POR or approved budget exists. The value is populated from the approved budget. The field becomes visible when a POR is created; however, if an approved budget does not exist, the budget fields are automatically populated with null cost values.
    • The Budget Equals Planned Values check box is selected and detailed financial plans do not exist.
    Budgeted Operating %

    Specifies the percentage of total budget costs that come from operating. This read-only field is calculated from the Budgeted Operating Cost field value.

  6. Save your changes.

Back to Top

Select the Method for Collecting Cost Information and Create the Plan

Create the detailed financial plan to update capital and operating costs automatically from either task assignments or team allocations.

If you plan to populate your financial plan using task assignments, you can override the investment Cost Type setting at the specific task level. Set the investment default for the cost type when you create the financial plan.

For example, consider an investment with 90 tasks that break down into the following cost types: 80 operating cost tasks and ten capital cost tasks. In this case, the financial manager sets the investment Cost Type attribute to Operating. This setting automatically assigns the Operating cost type to all tasks and the 80 operating cost tasks are correctly identified. For the ten tasks that are capital cost, the financial administrator specifies the cost type at the task level to override the default setting.

Follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type.
  2. Open the investment and click Financial Plans.
  3. Open the Financial Plans menu and click Cost Plans.

    The cost plans list appears.

  4. Open the Actions menu, and from General, click one of the following options:

    The properties page appears showing the default values from the associated entity and investment. You can accept these default values, or you can change them.

  5. Enter a name, ID, and description for the cost plan.
  6. Select Cost Type from the Grouping Attribute drop-down list.
  7. Save your changes.

Back to Top

Set the Cost Type for Specific Investment Tasks

Cost plans with information that is populated from task assignments can have some tasks with a cost type different from the default. You can indicate a cost type for a specific task that overrides the default cost type that is selected for the plan.

Example 1

The Cost Type attribute for an investment is set to Operating. However, there are some tasks or task hierarchies that require the Capital cost type. In this case, you select the Capital cost type for only those tasks. When you populate the cost plan from tasks assignments, the plan displays a breakdown of capital and operating costs by line item.

Example 2

The Cost Type attribute for an investment is set to Operating. The investment has a parent task with a cost type of Capital. The parent task has two children tasks: Task 1 has a cost type of Operating and Task 2 has no cost type selected.

In this case, Task 1 has Operating specified and Task 2 inherits the cost type Capital from its parent task. When a cost plan is created using New from Task Assignments, two rows get created, one for Operating costs and one for Capital costs.

Note: The Cost Type field does not display out-of-the-box for tasks. The system administrator must configure the Tasks view in in Studio to display the field.

Follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type.
  2. Open the investment and click Tasks.
  3. Open a task and select Capital or Operating from Cost Type.

    Note: A child task inherits the selected value, unless it has a different cost type selected.

  4. Save your changes.
  5. Repeat this procedure for each task that has a different cost type than the one selected for the investment.

Back to Top

Set the Capitalization Percentage for Investment Team Allocations

To show capital costs by team allocation, specify the capitalization percentage value for team members. For example, you have a team of six people who are assigned to a project. You can specify a capitalization percentage for each team member. Each member can have a different percentage. The cost plan displays the capital and operating costs for team members for whom you set a capitalization percentage.

Follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type.
  2. Open the investment and click Teams.
  3. Click Teams to open the menu, then click Staff.
  4. Click the properties icon next to a team member name.
  5. Enter a value in the Capitalization % field.

    The value is used to calculate the percentage of operating cost and capital cost for the employee allocation.

    Note: The Capitalization field does not display out-of-the-box for teams. The system administrator must configure the Teams view in in Studio to display the field.

  6. Click Save and Return.
  7. Repeat this procedure for each team member for whom you want to display both capital and operating cost percentages.

Back to Top

Verify that Capital and Operating Costs Display Correctly

Verify that the investment capital and operating costs display on the following pages:

To view the Financial Summary page, follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type (for example, Projects).
  2. Open the investment and click Properties to open the menu.
  3. Click Budget.

To view the Cost Plans Detail page, follow these steps:

  1. Open Home, and from Portfolio Management, click the appropriate investment type.
  2. Open the investment and click Financial Plans.
  3. Open the Financial Plans menu and click Cost Plans.

    The cost plans list appears.

  4. Click the name of the POR.

When the capital and operating costs appear on both pages, you have correctly displayed this information.

Back to Top