Configure the Gantt Chart Display Settings

Gantt charts appear on various pages throughout CA Clarity PPM. The steps to change the display settings are the same from any page with a Gantt chart.

By default, Gantt charts display only one bar, the primary bar. You can change the information that is displayed in that bar (Total Effort, by default). You can also add a secondary bar to display complimentary or contrasting data. You can also change the time configurations that display in the chart.

Follow these steps:

  1. From a page that contains a Gantt chart, open the Options menu and click Configure.
  2. Open the List Column Section menu, and click Fields.
  3. Click the Properties icon next to Column Label. For example, Schedule.
  4. Configure the Gantt chart display settings.
  5. Save your changes.