When you automatically populate a cost plan from the task assignment, the product uses the following values from the task assignments to populate the cost plan fields. If a value is not defined for an assignment, either the corresponding value on the investment is used or the field is left blank.
|
Value |
Task Assignment |
Primary Source |
Secondary Source |
|---|---|---|---|
|
Charge Code |
Resource or Role |
Task |
Investment. The field is blank if the value is undefined on the investment. |
|
Cost Type |
Resource or Role |
Task |
Investment |
|
Input Type Code |
Resource |
Resource |
None. The field is blank if the value is inactive or undefined on the resource, or if the resource is a role. |
|
Input Type Code |
Role |
N/A |
None. The field is blank if the task assignee is a role. |
|
Department |
Resource |
Resource |
Investment |
|
Department |
Role |
Staff OBS Unit |
Investment |
|
Location |
Resource |
Resource |
Investment |
|
Location |
Role |
Staff OBS Unit |
Investment |
|
Transaction Class |
Resource |
Resource |
None. The field is blank if the value is undefined on the resource, or if the task assignment is a role. |
|
Transaction Class |
Role |
Role* |
|
|
Resource |
Resource |
Task Assignee |
|
|
Resource |
Role |
N/A |
If the task assignee is a role, then the field is blank. |
|
Resource Class |
Resource |
Resource |
None. The field is blank if the value is undefined on the resource. |
|
Resource Class |
Role |
Role* |
None. The field is blank if the value is undefined on the role. |
|
Role |
Resource |
Task role |
Team role. If the team role is undefined, the resource primary role is used. The field is blank if the resource primary role is undefined. |
|
Role |
|
Task role |
Team role. If the team role is undefined, the team member (role) is used. |
* The role that is obtained for the Role attribute.
|