Previous Topic: Set Up Financial Management Processing OptionsNext Topic: Create the Cost/Rate Matrix


Financial Matrices

A matrix is composed of the following:

You can define a Cost/Rate matrix used during financial transaction processing to determine costs and billing or charge rates. You can create cost and rate matrices for labor, materials, equipment, and expense resource types.

You can establish default matrices at the system level, entity level, and investment level. CA Clarity PPM looks for and applies matrices first at the investment level, then at the entity level, and finally at the system level. You can set default rate locations at either the entity level or system level. If a matrix cannot be matched, you can enter costs and rates manually when you create transactions.

Set up currency before creating a cost/rate matrix.

More information:

Entities

How to Set Up a Cost/Rate Matrix

As the financial manager, you can ensure that standard costs and rates apply to all detailed financial plans and transactions for investments. Create a standard cost/rate matrix that provides default values from a centralized cost/rate matrix in the financial system. The standardized default information eliminates the need for defining costs and rates for different financial plans and transactions individually.

Populate the cost/rate matrix with the following types of financial values:

Example: Set up a Cost/Rate Matrix that is Based on Resource Class

The Document Management Company captures costs in the financial system using the resource class and the input type code of the resources that are assigned to their investments. The company has four different resource classes that are assigned to two different input type codes. The resource classes and input type codes have different costs that are associated with them. For example, a billable labor has an actual cost of $100 whereas a non-billable labor has no cost that is associated with it. Also, cost for non-labor resource classes is calculated as $1 x quantity.

To meet the corporate requirements, Sam the financial manager at Document Management Company sets up a cost/rate matrix with five different rows. Sam creates one row for each resource class (labor and non-labor) and input type code combination and populates the row with the appropriate cost. The matrix rows define the criteria for applying costs to resources for transaction processing. The following table shows the matrix rows:

From Date

To Date

Resource Class

Input Type Code

Actual Cost

1/1/14

12/31/14

Labor

Billable

$100

1/1/14

12/31/14

Labor

Non-Billable

$0.00

1/1/14

12/31/14

Expense

*

$1.00

1/1/14

12/31/14

Materials

*

$1.00

1/1/14

12/31/14

Equipment

*

$1.00

The following diagram describes how the financial manager sets up a cost/rate matrix:

The diagram shows the flow of tasks for setting up a cost/rate matrix

Follow these steps:

  1. Verify the prerequisites.
  2. Create the cost/rate matrix.
  3. Assign columns to the matrix.
  4. Add rows to the matrix.

Verify the Prerequisites

Before you set up a cost/rate matrix, complete these prerequisites:

Understand

Verify that you understand the following financial management concepts:

Note: For more information about CA Clarity PPM financial management concepts, see the Financial Management User Guide.

Set up an entity

Verify that you have created and set up a financial entity.

Note: For more information about setting up an entity, see the How to Set Up a Financial Entity scenario.

Plan the matrix

Verify that you have the gathered the following information that is required to plan for your matrix: