You move resource allocations backward or forward in time to shift or scale all or a portion of the resource allocations for an idea. As you move data, segmented allocation dates are kept intact, even when the percent allocated for each segment changes. Shifting allocations is useful for projecting allocations beyond the allowable time-scaled view, which only extends for six months.
Example: An allocation starts on May 1 and continues at its default rate of 100 percent through the end of May. Then it extends through June at the reduced allocation of 50 percent. You can shift the allocation to start from June 1 to July 2 (for 31 calendar days) at 100 percent, and continue to August 2 at 50 percent. You can also shift allocations for time spans that contain no segments.
You can also reset the staff allocations for an idea in the following ways:
Follow these steps:
The staff list page appears.
The allocations page appears.
Data shifts according to the dates you enter in the fields.
Note: Click More on the team staff page and team detail pages of an idea to use the Set Allocation option.
The allocations page appears.
In the General section of the page, set the following allocations for the selected team members:
Defines the date of starting work on the idea. Select the Reset to Match Investment Start Date check box to reset the resource staffing requirements on the idea to match the idea start date.
Defines the last date of working on the idea. Select the Reset to Match Investment Finish Date check box to reset the resource staffing requirements on the idea to match the idea finish date.
Defines the percentage of time for allocating the resource to the idea. You can enter 0 percent. The Allocation and Allocation % columns on the Idea Team: Staff page reflects the change.
Displays the resource or role booking status.
Values
The confirmation page appears.
Click Yes to commit the planned allocation to equalize the hard allocation to the planned allocation for the resource. Commit after editing the planned allocation segment for hard-booking the segments for a resource. A hard booking status for a resource signifies full commitment. To use the Commit Planned Allocation option, click More on the Idea Team: Staff page and Idea Team: Detail pages and select the option.
Note: Committing planned allocation does not reset the default allocation percentage. This action copies the planned allocation into the Hard Allocation section of the resource Staff Member Properties page. The Hard Allocation section displays on the page depending on your Mixed Booking settings.
The confirmation page appears.
Click Yes to set the planned allocation to equal the committed hard-booked allocation. If soft-booked planned segments display in the Planned Allocation section they are removed. All segments are then reset to equal the hard-booked segment. The % Allocation and Allocation column values change. The Booking Status value appears Hard because the allocation is fully committed.
Note: The Accept Hard Allocation option displays on the page depending on your Mixed Booking settings.
|
Copyright © 2013 CA.
All rights reserved.
|
|