Control Accounts (CA)

Control accounts (CA), or cost accounts, represent the work that supports a deliverable. CA helps to aggregate and report on earned value for their associated work packages.

This section contains the following topics:

Create Control Accounts

View a List of and Open Control Accounts

Edit Control Accounts

View Control Account Authorized Budget

Control Account Baselines

Enter Reprogramming Adjustments for Control Accounts

Monitor Control Account Performance

Delete Control Accounts

Create Control Accounts

You can create control accounts (CA) in the CWBS element for the deliverable activities that will occur within the upcoming reporting periods. Create control accounts on the lowest level CWBS root node element.

As control accounts are formed, the contract program manager can distribute the contract undistributed budget to the control accounts. During the execution of a contract, you can create additional control accounts as deliverables represented by summary level planning packages (SLPP) due.

Important! Create the contract and the lowest level CWBS root node element on your CWBS hierarchy pertaining to the control account before creating the control account.

Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Contract WBS.

    The contract WBS page appears.

  3. Expand the CWBS hierarchy to locate the CWBS element associated to the new control account, and click the CWBS element name.

    The properties page appears.

  4. Click Control Accounts.

    The list page appears.

  5. Click New.

    The create page appears.

  6. Complete the following fields:
    Control Account Name

    Defines the control account name.

    Required: Yes

    Control Account ID

    Defines the control account unique identifier.

    Required: Yes

    Description

    Defines the control account description.

    OBS

    Defines the organizational department, or subcontractor/ vendor group responsible for delivering the work within the control account. Select a unit from the same OBS structure as you selected for the contract. If you select a different unit, the baseline, and earned value metrics do not aggregate in the CPR reports.

    Required: Yes

    Control Account Manager

    Defines the name of the control account manager (CAM). The resource is typically a member of the control account OBS unit.

    Required: Yes

    Earned Value Analyst

    Defines the name of the control account earned value analyst.

    Financial Analyst

    Defines the name of the control account financial analyst.

    Scheduler

    Defines the name of the control account scheduler.

    Status

    Specifies the control account status.

    Values: Rejected, Unapproved, or Approved

    Default: Not selected

    Authorized Budget (BAC)

    Defines the control account authorized budget (BAC). You require to manually enter the value. Use the field to monitor the progress of the authorized budget against the work package aggregated BAC. A variance can indicate corrective action is required.

    Budget (BAC)

    Displays an aggregation of the sum of BAC of all the control account work packages.

    Start Date

    Defines the control account planned start date.

    Finish Date

    Defines the control account planned finish date.

  7. Save the changes.

View a List of and Open Control Accounts

View a list of control accounts across all contracts using the control accounts list page. You cannot create or delete control accounts from the list page.

Follow these steps:

  1. Open the control account.

    The control accounts page appears.

  2. Click the name of the control account to open.

    The properties page of the control accounts appears.

Follow these steps:

  1. Open the CWBS element.

    The properties page appears.

  2. Click Control Accounts.

    The CWBS control accounts page appears.

  3. Click the name of the control account to open.

    The properties page appears.

More information:

Work Packages (WP)

Summary Level Planning Packages (SLPP)

View a List of and Open Work Packages

Edit Control Accounts

Follow these steps:

  1. Open the control account.

    The control accounts page appears.

  2. Click the name of the control account to edit.

    The properties page appears.

  3. Edit the following fields:
    Control Account Name

    Required. Defines the control account name.

    Control Account ID

    Required. Defines the control account unique identifier.

    Description

    Defines the control account description.

    OBS

    Required. Defines the organizational department, or subcontractor/ vendor group responsible for delivering the work within the control account. Select a unit from the same OBS structure as you selected for the contract. If you select a different unit, the baseline, and earned value metrics do not aggregate in the CPR reports.

    Control Account Manager

    Required. Defines the name of the control account manager (CAM). The resource is typically a member of the control account OBS unit.

    Earned Value Analyst

    Defines the name of the control account earned value analyst.

    Financial Analyst

    Defines the name of the control account financial analyst.

    Scheduler

    Defines the name of the control account scheduler.

    Status

    Specifies the control account status.

    Values: Rejected, Unapproved, or Approved

    Default: Not selected

    Authorized Budget (BAC)

    Defines the control account authorized budget (BAC). Manually enter the value. Use the field to monitor the progress of the authorized budget against the work package aggregated BAC. A variance can indicate the necessity for corrective action.

    Budget (BAC)

    Read-only. Displays the aggregate BAC of all the control account work packages.

    Start Date

    Defines the control account planned start date.

    Finish Date

    Defines the control account planned finish date.

  4. Save the changes.

View Control Account Authorized Budget

Often the control account authorized budget (BAC) is driven by a bottom up number. In this case, enter the control account BAC after you define, schedule, and scope all of the control account's work packages. Use the control account Budget (BAC) field to compare the work package current aggregated BAC against your authorized budget. This display-only field displays an aggregation of the sum of BAC of all the control account’s work packages.

Follow these steps:

  1. Open Home, and from Earned Value Management, click Control Accounts.

    The control accounts page appears.

  2. Click the name of the control account.

    The properties page appears.

  3. View the authorized budget in the Budget (BAC) field, and save.

More information:

How to Work with Work Packages

Control Account Baselines

Control accounts are baselined when you baseline the contract.

More information:

Work Packages (WP)

Summary Level Planning Packages (SLPP)

Enter Reprogramming Adjustments for Control Accounts

During the course of executing a contract, reprogramming adjustments maybe required. The reprogramming decisions result in adjustments to individual control accounts. A reprogramming adjustment is represented as budget, cost, and schedule variances within an Over Target Baseline (OTB), or Over Target Schedule (OTS). Use the fields on the properties page of reprogramming adjustments to enter the total changes for a control account. The values appear on the CPR Format 1 report, in Section 8 - Columns 12a, 12b and 13.

Follow these steps:

  1. Open the control account.

    The properties page appears.

  2. Open the Control Accounts menu and click Reprogramming Adjustments.

    The reprogramming adjustments properties page appears.

  3. Complete the following fields:
    Cost Variance

    Defines the reprogramming adjustment cost variance aggregated from all costs recorded against control accounts at this level.

    Schedule Variance

    Defines the reprogramming adjustment schedule variance aggregated from all costs recorded against control accounts at this level.

    Budget

    Defines the reprogramming adjustment budget aggregated from all costs recorded against control accounts at this level.

  4. Save the changes.

More information:

Work Packages (WP)

Summary Level Planning Packages (SLPP)

Contract Performance Report (CPR) Format 1 - WBS

Monitor Control Account Performance

Use the control account dashboard page to monitor control account performance. The page displays the EV History portlet, which contains the earned value history data based on the work packages. As time progresses, each new reporting period is displayed on the graph.

Optionally, you can show projected data on the graph. Your CA Clarity PPM administrator sets up the Update Earned Value History - Contracts job parameters to project ACWP, BCWP, and BCWS. Then, you can run the job to view the earned value history.

Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

To customize the page, add or remove portlets using the dashboard of the control account layout portlet page in Studio.

Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

More information:

Summary Level Planning Packages (SLPP)

Update Earned Value History - Contracts Job

Delete Control Accounts

You cannot delete control accounts that are active or have a baseline. When you delete a control account that has defined work packages, the associated work packages are also deleted.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Contract WBS.

    The contract WBS page appears.

  3. Expand the CWBS hierarchy to locate the CWBS element associated with the control account, and click the name of the CWBS element.

    The properties page appears.

  4. Open the Control Accounts menu.

    The properties page appears.

  5. Select the check box next to the control account, and click Delete.

    The confirmation page appears.

  6. Click Yes.