Choose new grouping attributes and time period types for the budget by creating and submitting a new cost plan that replaces the approved budget plan.
For example, when planning for an upcoming project, you provide an estimated budget with the roles that you think you need. Before the start of the project, you create a cost plan with the actual resources and change the grouping attributes to include Department and Location. You can then submit the new cost plan to replace the approved budget plan.
Example: Submit a New Cost Plan and Replace the Budget
Alice fills all the positions for the team and knows the cost of each resource. She has resources in two locations and wants to group by department and location. Additionally, the product manager asks that she use monthly time periods instead of quarterly. Alice creates a cost plan and adds each resource with their cost details. She makes the following selections to the properties of the cost plan:
Alice saves her changes as ProjectA_actualCP-00, and submits the new budget for approval.
Follow these steps:
Note: For more information about creating cost plans, see the Financial Management User Guide.
Note: If the cost plan is already the plan of record, skip this step.
The Submit Option field lists Replace as the only available option. You must replace the budget when the grouping attributes or the fiscal time period type are different from those selected properties for the existing budget.
Note: If you receive the following message, another cost plan for the investment exists as a submitted budget plan.
Error:A submitted budget already exists.
The submitted budget plan must be approved or rejected before you can submit another plan for approval.
You have submitted a cost plan for approval that replaces the existing budget.