Remove Resource Actual Usage on Tasks

Use the following procedure to remove actuals for a specific resource assigned to a task. You can also use this procedure if you are using Open Workbench with CA Clarity PPM and the resource's track mode—the method of time capture—is set to none in CA Clarity PPM.

Note: See the Resource Management User Guide for more information.

You can remove actuals or you can convert any actual usage that has been recorded after the date back to ETC usage.

To remove a resource's actuals by converting them to ETC

  1. Right-click a task in the view and click Assignments.

    The Resources tab on the Task Properties dialog box opens.

  2. In the Assigned Resources grid, do one of the following:
  3. Click OK.

    The Task Properties dialog box closes.

More information:

Update Resource Data

Define Resource or Role General Properties and Availability

Edit Resource Periodic Availability

Define Resource Advanced Properties

Define Resource Calendar

Add Notes

How to Enter Pending Estimates

About Editing Multiple Resources