Previous Topic: Define Resource or Role General Properties and Availability

Next Topic: Define Resource Advanced Properties

Edit Resource Periodic Availability

A resource’s availability can vary during a project. Any resource that has scheduled holidays (other than weekends) or vacations has variable availability. You can change the availability for a resource for any given period by editing the resource calendar.

For example, a resource is available 8 hours per day for the first 20 days of a project, but for the next 10 days, the resource has a scheduled holiday. You can change a resource’s periodic availability using the Availability field in a view, or by scheduling holidays in the resource’s calendar.

More information:

Update Resource Data

Edit Calendars