Previous Topic: Issues Associated with Tasks

Next Topic: Associate Existing Key Tasks with Issues


View a List of Issues Associated with Tasks

Use the following procedure to view a list of issues. This page displays the name for the issue, priority, target resolution date, and the name of the assignee. Resources with project access can view the issues.

Follow these steps:

  1. Open the project and click Risks/Issues/Changes.

    The risks page appears.

  2. Open the Risks/Issues/Changes menu and click Issues.

    The issues page appears.

  3. Click the name of the issue.

    The issue main page appears.

  4. Click Associated Tasks.

    The task-associated issues page appears.

More information:

Associate Existing Key Tasks with Issues