About Task Requisitions

The following is a high-level overview of the flow of tasks that the project and the resource managers perform. The aim is to fulfill project staffing requirements through the process of creating and submitting requisitions.

See the Resource Management User Guide for more information.

  1. The project manager defines staffing requirements by adding soft-booked resources or roles as project team members.
  2. The project manager creates requisitions based on the predefined staffing requirements.
  3. The project manager submits new requisitions so resource managers can start looking at them. The requisition is routed to the appropriate resource managers based on the default booking manager defined for the resource or role in the requisition.
  4. The resource manager addresses requisitions by proposing a list of resources. The resource manager can also decline a requisition. In both cases, the project manager is notified.
  5. The project manager reviews the proposed allocations and either:
  6. The project manager can make the following changes to the resource allocation after a resource is hard-booked to a project: