You can display cost metrics in the Gantt view without creating a current baseline.
The fields do not display, by default, on the page - requires personalizing the page. Alternatively, let your CA Clarity PPM administrator configure the Gantt list column view for the task object at the system level to display the columns.
See the Personalizing CA Clarity PPM User Guide for more information.
See the Studio Developer’s Guide for more information.
The following cost metrics are available:
Displays the system-calculated value of Actual Cost of Work Performed (ACWP), which is the total direct cost incurred in performing work based on posted actuals. ACWP is calculated at the following levels:
ACWP = Sum of Actual Cost for all the assignments on the task
ACWP = Sum of ACWP for all detail tasks in project
ACWP = Sum of ACWP for all summary tasks in project
Current Baseline Required: No
Displays the system-calculated value of Estimate To Completion (ETC), and is calculated based on the following formula:
ETC (Cost) = remaining labor cost + remaining non-labor cost
Current Baseline Required: No
Displays the system-calculated value of Estimate At Completion (EAC). This calculation is most often used when current variances are seen as typical of future variances. The calculation is based on the following formula:
EAC (T) = ACWP + ETC
Current Baseline Required: No
| Copyright © 2012 CA. All rights reserved. |
|