Once a risk is successfully mitigated, change the status of the risk to "Closed" and then enter the final resolution for the risk. A detailed resolution can help you recall the outcome of a risk response strategy when planning, or approaching future project risk plans.
Follow these steps:
The risks page appears.
The risk main page appears.
Specifies the status of the risk.
Values: Open, Work in Progress, Closed, or Resolved
Default: Open
Select "Closed" as the status.
Defines how the risk is resolved.
The risk is closed.