Resolve and Close Issues

Once an issue is resolved, change the status of the issue to "Closed." Then, enter a final resolution for the issue. A detailed resolution can help you recall the outcome of an issue when planning or approaching future projects issue plans.

Follow these steps:

  1. Open the project and click Risks/Issues/Changes.

    The risks page appears.

  2. Open the Risks/Issues/Changes menu and click Issues.

    The issues page appears.

  3. Click the name of the issue.

    The issue main page appears.

  4. Complete the following fields and save:
    Status

    Specifies the status of the issue.

    Values: Open, Work in Progress, Closed, or Resolved

    Default: Open

    Required: Yes

    Select "Closed".

    Resolution

    Defines the final resolution of the issue after the matter is resolved.

    Required: No