Associate Existing Tasks with Risks

Creating an association between the risk and the key task, helps you view the association on the task associated risks page.

Follow these steps:

  1. Open the project and click Risks/Issues/Changes.

    The risk page appears.

  2. Click the risk name.

    The risk main page appears.

  3. Click Associated Tasks.

    The risk associated tasks page appears.

  4. Click Add Existing Tasks.

    The select tasks page appears.

  5. Select the check box next to the key task to associate the risk, and click Link To.

    The task is associated to the risk.

More information:

View a List of Risks Associated with Tasks