Update Project Baselines

Use this procedure to update master project and subproject baselines. You can update existing project baselines to reflect changes to task assignments and other information, such as recently posted actuals. When you update a baseline, it becomes the current baseline revision.

When you update a project baseline, the changes to task assignments, estimates, and the financial summary from the last update get included. Updating a baseline changes its values accordingly.

Follow these steps:

  1. Open the project.

    The properties page appears.

  2. Open the Properties menu, and from Main, click Baseline.

    The baseline properties page appears.

  3. Select the check box next to the baseline to update, and from the Actions menu, click Update Baseline.

    The confirmation page appears.

  4. Click Yes.

More information:

Baselines

Create New Baselines (Investments)

Edit Baselines (Investments)

Define the Current Baseline (Investments)

Update Task Baselines

Subproject Baselines

Update Task Baselines