You can edit dependency relationships for external dependencies using the Dependencies tab on the Task Properties dialog box or using the External Dependencies dialog box. You cannot move the dates on external tasks or modify it within your project; the externally linked task's properties are read-only and do not include resource or dependency information.
Note: You can only access the Dependencies tab on the Task Properties dialog box if the externally dependent task has a predecessor relationship with the task in your project.
To edit an external dependency
The External Dependencies dialog box opens.
Specifies the task's dependency relationship.
Default: Successor
Options: Successor or Predecessor
Specifies the constraint type to be placed on the task's start or finish date.
Default: Finish-Start
Options: Start-Start, Start-Finish, Finish-Start, or Finish-Finish
Defines the number that represents the days or percent to indicate the amount or time between, or overlapping, the task start or finish dates.
Note: The constraint type used is the type you specify.
Specifies the lag type.
Default: Daily
Options: Daily or Percent
The external task dependency is modified.
| Copyright © 2011 CA. All rights reserved. |
|