You can autoschedule projects from a finish date to help you find out on which date your project needs to start in order to meet a required finish date. When you choose to schedule your project based on its finish date, Autoschedule performs three traversals of the project. In the second and third traversals it goes over the tasks backward first and enforces finish constraints over start constraints so that the project is scheduled to start as late as possible.
When you run Autoschedule using a project's finish date, it does the following:
To autoschedule your project from a finish date
The Autoschedule dialog box opens.
The Start Date field toggles to the Finish Date field. The current project finish date displays in the Finish Date field.
The project or selected tasks are scheduled from the finish date.