Display Pending Estimates Data in Views
To view pending estimates in a spreadsheet view, such as the Gantt Chart view, you must first create a new view that includes the fields that display pending estimate data.
Add the following fields to the task detail pane:
- Task Estimate to Complete
- Task Pending Estimates
- Task Pending Estimate Override?
- Task Pending Actuals
- Task Pending Actuals?
More information:
How to Enter Pending Estimates
Accept Pending Estimates
Reject Pending Estimates
Save Views
Add Field Names to Views
|