Manage Projects › Update Task Data › About Defining Task Resources Properties › Release Resources from Task Assignments
Release Resources from Task Assignments
Use the Resources tab on the Task Properties dialog box to release resources from task assignments. When you release a resource from a task assignment, the resource is still available for assignment to other tasks in the project.
To release a resource from a task assignment
- Right-click a task and select Modify from the shortcut menu.
The Task Properties dialog box opens.
- Select the Resources tab.
A list of the task's resource assignments displays.
- In the Assigned Resource grid, select the resource assignment you want to remove, and click Release.
The resource name is removed from the Assigned Resource grid.
- Click OK.
More information:
About Defining Task Resources Properties
Define Resource Actual Usage on Tasks
Define Resource Estimate to Complete on Task
Define Resource Maximum Percentage on Tasks
Transfer Task Assignments between Resources
|