Schedule Subnets

Subnets are a set of tasks in a project that have dependencies among themselves. During Autoschedule, you can choose to calculate and display separate critical paths for each subnet and for each task that does not have dependencies. Otherwise, only one critical path—the longest path—is calculated for the project. Use the Subnets (All Projects) check box on the Scheduling tab to specify whether you want CPM to calculate the project's critical path separately for each subnet.

There are several key benefits to scheduling subnets:

To set up your project to calculate separate critical paths

  1. Select File, Properties.

    The General tab on the Project Properties dialog box appears.

  2. Click the Scheduling tab.

    A list of the project's scheduling properties display.

  3. In the Critical Path section of the page, select the Subnets (All Projects) check box.

    Your project is set up to calculate separate critical paths.

  4. Do one of the following:

    Separate critical paths are calculated for your project.