Inserting subproject tasks into a master project allows you to pull out sections of projects and evaluate the work being done by your team across many projects from the master project.
You can insert a subproject task into your master project using the Open Subprojects dialog box. This dialog box is a version of the standard Windows Open dialog box.
If your master project is linked to an Open Workbench .rmp project file via a subproject association, you cannot save it back to CA Clarity PPM.
To insert a project task as a subproject task into a master project
The Open Subprojects dialog box opens.
Defines the type of file you want to open.
Values:
Note: You cannot insert XML project files into master projects.
A list of available projects display.
Specifies whether you want to add the project, subproject, or subproject task in read-only mode in the master project. When you insert a subproject into a master project in read-only mode, any changes you make to the subproject from the master project are not saved.
Default: Cleared
Note: This check box is only available if you have edit rights to the selected project, subproject, or subproject task. If you opened the master project in read-only mode, this check box is selected and is unavailable.
Specifies if you want the ability to create subprojects from the inserted subproject.
Default: Cleared
Note: If you are inserting a partial subproject, this check box is selected and unavailable.
Displays the name of the selected task or summary task.
The selected subproject task is inserted into the master project.