Override Task Lock during Autoschedule

You can override the lock on tasks while autoscheduling. For example, if you have a task that is locked between February 25, 2008 and April 4, 2008, Autoschedule distributes the assignment's ETC to the task between the two dates. If you do not override the lock and Autoschedule changes the task's end date to April 25, 2008, the assignment's ETC remains between February 25, 2008 and April 4, 2008. However, if you choose not to override the lock, the assignment's ETC is distributed between February 25, 2008 and April 25, 2008, per the assignment's loading pattern.

When scheduling locked tasks using this option, Autoschedule adheres to the following rules:

To override the task lock during Autoschedule

  1. Select Autoplan from the Schedule group in the Project ribbon.

    The Autoschedule dialog box opens.

  2. Select the Schedule Assignments on Locked Tasks check box, and click OK.

    The project or selected tasks are scheduled and the lock on tasks is overridden.

More information:

Define Autoschedule Parameters

Lock Tasks in Place

Define Task Scheduling Constraints